Construction of Sakhalin TPP-2

Construction of Sakhalin TPP-2
Implementation into service of Sakhalin TPP-2 will provide reserves required energy infrastructure liability to satisfy industrial growth in region and population needs.
Current building stage
  • Development of design documentation
  • Obtaining permits
  • Conclusion of general agreement and equipment supplies
  • Preparation works
  • Building installation work
  • Commissioning works
  • Putting into operation
Project specifications
Power Plant will be built in Il'inskiy settlement in Tomarinskiy district of Sakhalin region. Will substitute retired capacities of operating Sakhalinskaya hydroelectrical power plant and increase total output of isolated Sakhalin island energy system. It also considers its possible economy development needs.
  • Electrical power 120 MW
  • Heating power 18.2 Gcal/hr
  • Main fuel local coal
Sakhalin region
  • General contractor JSC «TEK Mosenergo»
  • General project designer JSC «Institut Teploelecroproect»
  • General equipment supplier JSC «TEK Mosenergo»
Investment projects 1