Construction of CHPP Vostochnaya

Construction of CHPP Vostochnaya
CHPP "Vostochnaya" is a new heat and electicity generating facility that is being constructed by "RAO Energeticheskie systemy Vostoka" Corp. Power plant construction is the key project of this corporation in the south of Primorye. New facility is constructed in location of active boiler house and is meant to replace Central Boiler House retired capacities.
Current building stage
  • Development of design documentation
  • Obtaining permits
  • Conclusion of general agreement and equipment supplies
  • Preparation works
  • Building installation work
  • Commissioning works
  • Putting into operation
Project specifications
The need for new CHP-plant construction is caused by estimated heat supply deficit due to new residence areas such as already implemented "Snegovaya Pad" and "Patrokl". New residence areas are in project as well. Implementation in service of CHPP "Vostochnaya" will provide 20% of total city power demand.
  • Electrical power 139,5 MW
  • Heating power 421 Gcal/hr
  • Main fuel natural gas
Vladivostok, Primorsky region,
2011-2016
  • General contractor CJSC «Energoremont»
  • General project designer CJSC «Sibirskiy ESTC»
  • General equipment supplier GE Packaged Power Inc.